Runway Extension
In order to better serve the surrounding communities the NAC has done its due diligence steps during 2007, and will complete in 2008 for a runway extension. This includes detailed reviews of the Economic, Environmental and Social implications of a longer runway (1,600 feet).
We have retained a Project Manager, who is working with a team of specialists on a number of issues, including;
- Detailed Site Plans
- Engineering Designs
- Environmental Mitigation Strategies
- Regulatory Requirements and Permits
The NAC also engaged Jacobs Consultancy to prepare a comprehensive business plan. The plan was divided into 3 base components; Market Forecasts for a 20-yr period, Infrastructure Requirements and Cost Projections.
Executive Summaries
|
|
In order to view the above file(s) you will require Adobe Acrobat Reader |
Public Communication
Apr 18, 2008 - Island Coastal Economic Trust Announces $5 - Million for Nanaimo Airport
- Click here for full media release.
Feb 29, 2008 - Provincial News Release - $11 - Million Supports Nanaimo's Community Vision
- Click here for full media release.
Jan 14, 2008 - NAC Public Information Meeting held at North Oyster School 13470 Cedar Rd.
- Questions from January 14th, November 22nd & answers to many more questions.......Click Here
Nov 22, 2007 - NAC Public Information Meeting held at Coast Bastion Hotel, Nanaimo
- Questions from November 22nd, January 14th & answers to many more questions.....Click Here
Sept 27, 2007 - NAC Open House at Parksville Community Centre
- Details from the event ......Click Here
Aug 22, 2007 - Collaborative Process Planned For Future Airport Development
- Click Here for full media release
Aug 17-19, 2007 - NAC Information Booth at the Vancouver Island Exhibition
June 14, 2007 - NAC Open House at Cedar Community Hall
- Details from the event.....Click Here
April 12, 2007 - NAC Public Meeting at the Coast Bastion Inn, Nanaimo where information was presented regarding the airport upgrades.
Please refer back to this site for updates.